BioProducts Laboratory


Plant on roof Fume Cupboard Service Outlets Plant Room Low level storage

| Project: |
Building 21 - Fume Cupboard Replacement |
| Scope: |
Strip out existing fume cupboards; supply new fume cupboards and laboratory furniture; modify existing fume extraction, supply air and general ventilation systems including supply of new extract fans; disconnect and reconnect associated mechanical and electrical services; redecorate walls and make good floor finishes and interface with ceiling; provide a temporary building for use as a laboratory for the duration of the works. |
| Value: |
£117,000 |
| Date Completed: |
May 2007 |
Replacement fume cupboards
Extract fans & discharge stack Fume Cupboard

|